A 5-a-side pitch costs $57,000 to $110,000 for the surface package on a typical 1,200 sqm site — base, drainage, turf and install. Add fencing and floodlights and you are at $78,000 to $153,000. The spread is that wide because most of the money is not in the grass. It is in what goes underneath it, and in whether the base was built to drain.
We supply the turf for pitches like this, and we see the same four mistakes on nearly every first-time build. This is the line-by-line breakdown, the base build-up that actually works, and the spec sheet to send to a contractor so you are comparing like for like.
First, what "5-a-side" actually measures
The playing area most commonly specified is 40m × 20m, following FA and FIFA small-sided guidance. That is 800 sqm of grass you can play on. But you cannot buy 800 sqm of turf, because the ball has to be able to stop before it hits a fence.
Run-off is the number people forget. Three metres on all four sides is the usual minimum, which gives you 46m × 26m = 1,196 sqm. Add 5–10% for cutting waste, seam overlap and the odd mis-measure, and you are ordering around 1,300 sqm.
If your site can only take 2m of run-off, the pitch still works, but the fence becomes part of the game — players will use it to stop the ball rather than controlling it, and the surface near the fence takes far more abrasion.
Pitch sizes and turf area, side by side

A finished 5-a-side footprint: the turf area is the marked rectangle plus the run-offs, not the fence line.
Use this to find your order quantity before you talk to anyone. Areas include 3m run-off on all sides; the last column adds 8% waste.
| Format | Playing area | With 3m run-off | Order (incl. 8%) |
|---|---|---|---|
| 5-a-side | 40 × 20 m (800 sqm) | 46 × 26 m (1,196 sqm) | ~1,300 sqm |
| 7-a-side | 60 × 40 m (2,400 sqm) | 66 × 46 m (3,036 sqm) | ~3,280 sqm |
| 9-a-side | 80 × 50 m (4,000 sqm) | 86 × 56 m (4,816 sqm) | ~5,200 sqm |
| 11-a-side | 105 × 68 m (7,140 sqm) | 111 × 74 m (8,214 sqm) | ~8,870 sqm |
Roll width changes the arithmetic. Our turf comes in 2m and 4m rolls, and a 4m roll on a 26m-wide site leaves less offcut than 2m — see how much turf fits in a container if you are importing rather than buying locally.
The base: four layers, in this order
This is where 60–70% of your budget lands, and where a cheap build fails two winters later.
1. Subgrade
Strip the topsoil, then compact and level the formation. It needs to be firm enough that a plate compactor leaves no footprint, and it needs the fall built in here — not corrected later in the aggregate. Get this wrong and no amount of stone on top will fix the puddle.
2. Drainage
Two options. A herringbone network of perforated pipe in a gravel trench, running to a soakaway or attenuation crate, handles heavy rain and is what most full-size pitches use. A porous sub-base alone — no pipes, water percolating straight through — works on free-draining ground and saves real money, but only if the soil underneath drains, which you cannot assume.
Design the system for roughly 20mm of rain per hour and give the surface a fall of 0.5–1% across the pitch. Flat is not level; flat is a lake.
3. Sub-base
MOT Type 1 or an equivalent graded crushed stone, 100–150mm for a 5-a-side, 150–200mm for a full-size pitch where maintenance vehicles drive on it. It must be laser-levelled and rolled to a true plane, because every ripple in the stone is a ripple in the playing surface. Nothing above it can hide a bad sub-base.
Lay a geotextile separation membrane between subgrade and stone. It costs very little and stops fines migrating up into the stone, which is what turns a free-draining base into a sponge over five years.
4. Shockpad or e-layer
A 10–15mm prefabricated shockpad sits between the stone and the carpet. Two reasons to fit one: player safety (head impact on a hard base) and surface feel. Two reasons not to: cost, and it is not always required.
If you are going non-infill on a hard base, fit one. The turf itself provides almost no energy absorption, and a 40mm non-infill carpet laid direct on stone plays fast and punishes falls. If you are using a sand-and-rubber infill profile, the infill is doing that job already.
Infill or non-infill for a 5-a-side
Non-infill is the right answer for most small-sided pitches, and it is not a cost compromise. It plays faster, the ball rolls truer, there is no rubber to migrate into drains or boots, and there is no top-up line in the maintenance budget.
The trade-off is temperature and slide. Non-infill surfaces run hotter in direct sun and offer less give on a sliding tackle. For a community 5-a-side that is an acceptable trade; for a competitive surface, the filled build still wins.
Full breakdown of the two systems, including which pile heights each one needs, is in infill vs non-infill football turf. If you already know you want non-infill, our 30/50mm non-infill football turf is the product most 5-a-side builds specify.
What it costs, line by line
Figures below are for a 1,200 sqm 5-a-side in a developed market, materials and labour. They are budget ranges, not quotes — ground conditions and local labour move them by 30% either way.
| Item | Low | High | Notes |
|---|---|---|---|
| Site strip and subgrade prep | $8,000 | $20,000 | Depends on spoil removal and access |
| Drainage | $10,000 | $25,000 | Herringbone + soakaway; porous base is cheaper |
| Sub-base, 100–150mm | $12,000 | $20,000 | Stone, haulage, laser level, rolling |
| Geotextile | $1,500 | $3,000 | Do not skip this line |
| Shockpad, 10–15mm | $10,000 | $18,000 | Optional on filled systems |
| Turf carpet, ~1,300 sqm | $7,800 | $10,400 | 40mm non-infill at $6–8/sqm |
| Edging, adhesive, lines, install | $8,000 | $14,000 | Perimeter restraint is structural |
| Surface subtotal | $57,300 | $110,400 | ≈ $48–92/sqm |
| Fencing, 3m, ~144 lm | $9,000 | $18,000 | Twin-bar or chain-link |
| LED floodlights | $12,000 | $25,000 | 4–6 columns, 200–300 lux |
| Total | $78,300 | $153,400 |
The turf is 6–10% of the total on every build we have supplied. Anyone quoting you on carpet price alone is not quoting you on a pitch.
Where budgets go wrong
- Cheapening the sub-base. A 60mm stone layer instead of 120mm saves about $6,000 and costs you a surface that moves underfoot within two seasons. Every repair means cutting and re-seaming carpet.
- Ignoring the fall. A pitch laid flat holds water in the middle. Water under the carpet does not dry, and the backing delaminates.
- No edge restraint. Turf is dimensionally unstable — it expands in heat and contracts in cold. Without a fixed edge it creeps and opens seams at the corners.
- Buying on height. A 40mm carpet at 12,000 stitches is a different product from 40mm at 20,000. Height alone tells you nothing about wear; pile height and what it hides covers the numbers that do.
- Forgetting the last 10%. Spare turf, a box of adhesive, matching infill and a set of seam tools. Store them dry. In five years you will not be able to buy the same dye lot.
How long it takes

A full-size installation for scale. A 5-a-side follows the same sequence, just compressed into fewer days.
On a clear site with access for a 20-tonne wagon: strip and drainage 3–5 days, sub-base 3–4 days, shockpad and carpet 4–6 days, fencing and lights 4–6 days. Call it three to five weeks weather permitting, and do not schedule the opening fixture for week three.
Rain during sub-base work is the usual delay. Stone that is too wet cannot be compacted to a true level, and it will not dry under a membrane.
The spec sheet to send a contractor
If you want comparable quotes, ask every contractor to answer these in writing:
- Playing area and run-off dimensions, with the total turf area you expect them to price
- Sub-base depth and material specification, plus the compaction method
- Drainage design, outfall location, and the rainfall intensity it is designed for
- Surface fall, in percent, and where it falls to
- Turf specification: pile height, dtex, stitch rate, backing, and warranty on UV and wear
- Whether a shockpad is included, and its thickness
- Edge restraint type and depth
- What is excluded — spoil removal, power supply to floodlights, planning permission
If you send us the site dimensions and the format you are building, we will come back with a turf specification and a quantity rather than a price per square metre. Start from the football field turf range, or message us with the drawing. If you already know your area, the wholesale page lists prices per square metre and container loads.